We will bring the node offline to facilitate memory upgrade expected downtime is approximately 15 minutes.

We will bring the node offline to facilitate memory upgrade expected downtime is approximately 15 minutes.
Hi We are currently experiencing a large scale DDoS attack and it’s under investigation. All network services are showing large scale latency as a result. We will be blackholing the target IP and services should resume shortly. Update : 12:03 – services should be resumed now
We are scheduling a maintenance window tomorrow to perform a routine software upgrade on a firewall cluster in Carlow. This is a high availability cluster and the upgrades will be applied to the standby node. Access to dedicated servers (185.2.66.0/24) may be impacted for a few seconds as the firewall is failed over. Date: 2015-11-03 23:00 – […]
We have scheduled a maintenance window to remediate a critical electrical power issue in the Carlow Data Centre for Friday 30th October from 11:00 PM to 3:00 AM Saturday morning. The work requires a complete shutdown of electrical power to the Data centre for safety reasons because the electrical engineers will be replacing the Main […]