We are pushing updates to cp.blacknighthosting.com which will require a 5 minute window and cause a small outage on the platform. Hosting services will not be affected however access to the control panel may be down for a few minutes during the maintenance. Start 21:00 – finish 21:05
Author Archive | Tony Doherty
Scheduled maintenance of MV transformer and incoming circuit breaker in Carlow Data centre
We will be performing preventative maintenance on the MV Switchgear, Transformer and main incoming circuit breaker on Thursday 15th September on our Carlow site. The Carlow data centre will be operating on UPS/ generator power during this maintenance which is expected to last five hours. No impact to customer services is expected, however services should […]
Scheduled test and inspection of main breaker and generator redundancy in Carlow data centre
We have recently installed an additional fuel tank to extend the run time of our generators with the growing risk of power concerns over the coming months. We will be carrying out a full test of this functionality between Thursday 1st September and Friday 2nd September , during which the data centre will be operating […]
Network blip
At approximately 15:20 BST we observed disruption on our network to routes in the UK / Europe. One of our backhaul providers was undergoing emergency maintenance at the time, however this should not have been service affecting as it was a backup circuit. As the maintenance began, we noticed errors on the backup link with […]