We are scheduling an emergency maintenance window to upgrade four storage switches in Dublin tonight. Traffic will be moved to an alternate switch during each upgrade. Shared Hosting email services and Cloud1 should be considered at-risk during this maintenance.
Date: 2015-12-08 00:01 – 2015-12-08 06:00 UTC
Data Centre: Interxion DUB1
Impact: Cloud1/Shared Hosting Email
Update 08/12/2015 05:56: Due to time constraints, only two switches were upgraded during this maintenance window. A second maintenance window will be scheduled to upgrade the remaining switches.
Update 08/12/2015 19:20: A second maintenance window to complete this work is being scheduled for Wednesday night at 22:00:
Date: 2015-12-09 22:00 – 2015-12-10 06:00 UTC
Data Centre: Interxion DUB1
Impact: Cloud1/Shared Hosting Email