UPDATE : 30/11/2016
Unfortunately due to circumstances beyond our control we have to reschedule this maintenance to
Saturday Dec 10th 10:00 PM
Please note , we do not expect any service interruption, however all services in the data centre should be considered “at-risk” during this window.
**************************************
UPDATE : 24/11/2016
We are rescheduling the maintenance works planned for November 25th, due to availability concerns from US customers who wish to minimise any risk to their “Black Friday” retail operations.
We apologise for any inconvenience this may have caused.
The maintenance has been rescheduled to
Friday Dec 2nd @ 10:00 PM.
****************************************
We are scheduling a maintenance window to perform essential works on the power feeds in our Carlow Data Centre , Nov 25th 22:00 – 02:00Am
All equipment in this data centre is dual-fed and devices with single power supplies are now on Automatic Transfer Switches (ATS) . This means power should be maintained to all equipment but whilst working on the power feeds, services should be considered “at-risk” during the maintenance window.
Services at-risk
- Legacy Direct Admin servers
- Cloud2 Infrastructure
- NG shared hosting
The affected Legacy Hosting servers are shown below
CADOR
RAGNELL
GORLOIS
We will have engineers onsite and this POST will be updated should there be any issues