We are scheduling two maintenance windows to upgrade our edge routers in Blacknight Carlow. Customers may experience brief periods of packet loss and increased latency during these maintenance windows as the network re-converges.
- Date: 2025-09-14 06:00 – 2025-09-14 14:00 IST (UTC+1)
- Data Centre: Blacknight Carlow
- Router: ec-r02.bk0
- Impact: Reduced capacity
Update 2025-09-14: This maintenance is complete
- Date: 2025-09-18 00:01 – 2025-09-18 06:00 IST (UTC+1)
- Data Centre: Blacknight Carlow
- Router: ec-r01.bk0
- Impact: Reduced capacity